How long does a bathroom renovation take?

From demolition to handover, phase by phase, and what makes it take longer.

The MA Layan teamUpdated on 8 November 2026, 4 min read
Finished bathroom with walk-in shower and floating vanity unit

The short answer

How long a complete bathroom renovation takes depends on the size, on what we find behind the tiles and on the drying time after waterproofing. Before that comes the preparation: site visit, quote, your choice in the showroom and the delivery time of tiles and sanitaryware. After your approval we usually start within 6 weeks. We discuss the schedule per phase with you after the site visit.

What happens before demolition

Most of the time goes not into building but into preparation. After your request, we call you back and schedule a site visit at your home. There we take measurements, look at the pipes and the floor and discuss your wishes. You then receive a quote per item.

If you agree, you choose tiles, shower and sanitaryware in the showroom of our regular supplier. Their delivery time often determines the start date. We only start demolition once everything has arrived or is confirmed, so the crew does not have to wait and your bathroom is not left open for weeks.

How long does a bathroom renovation take per phase?

This is what a complete bathroom of average size looks like. You get your own schedule with the quote.

PhaseWhat happens
Demolition and removalTiles, sanitary ware and old pipes out, rubble removed straight away, rest of the home screened off
PlumbingNew water supply, drainage and electrics in the wall, false walls and niches
WaterproofingSealing walls and floor, then leaving to dry
TilingWall and floor tiles, including under a sloping roof
Fitting and handoverFitting sanitary ware, vanity unit and lighting, sealing, checking everything together

The whole process, from first phone call to handover

A complete renovation takes longer than a bathroom refreshed in one day with wall panels. That is mainly because of what happens before demolition. This is what the whole process looks like in Amsterdam:

WeekWhat happens
Week 1Phone call and site visit at your home
Week 2Quote per item
Weeks 2 to 4Choosing in the showroom, applying for VvE consent and a skip permit if needed
Within about 6 weeks of approvalDelivery of tiles and sanitary ware, then demolition starts
After thatDemolition, pipework, drying time, tiling and fitting
Last dayChecking everything together and handover

Your own schedule is set out in the quote.

What makes a renovation take longer

There is sometimes more behind the tiles than you can see. These are the five things we come across most often:

  • A poor subfloor or wood rot. We repair that first, otherwise the new tiling will crack.
  • Asbestos in old adhesive, sealant or vinyl flooring. Only a certified removal company may remove it, and that has to be scheduled first.
  • Moving the drain. A shower or toilet in a different place means more breaking out.
  • Made-to-measure items, such as a custom vanity unit, often have a longer delivery time.
  • VvE working hours in an apartment. If we may only drill at certain hours, it takes a little longer.

If we come across something like this, we discuss it with you first. We only carry out extra work after your written approval, with the price stated.

How we keep the schedule short

This is how we avoid the familiar problem of a bathroom left half finished because the next trade can't come yet.

Can you stay living at home?

Yes. Most clients simply stay at home during the renovation. We screen off the rest of the home and clean up every day. If you only have one bathroom or one toilet, we discuss how to solve that during the site visit.

“The demolition is done in a day or two. The time goes into preparing properly, so that we can keep going afterwards.”
The MA Layan team

Frequently asked questions

Is your question not listed? See all frequently asked questions or call us on 06 84 41 41 73.

First demolition, then pipework, drainage and electrics, then waterproofing and drying, then tiling and finally the sanitary ware, lighting and sealant. We always stick to that order.

Sometimes. If you choose tiles and sanitary ware that are in stock, we can start sooner. Call us and we will see what is possible.

With the quote. It states how many working days we need and when we can start.

Then we discuss it with you first. We only carry out extra work after your approval on paper, with the price included. That way you always know where you stand.

First we look, then we give a price

Request a site visit. We come round, measure up and then give you a quote per item.

Prefer direct contact?
Mon to Fri 07:30 to 18:30

Book a free site visit

Within 24 hours we call you to make an appointment.

After your approval we usually start within about 6 weeks

Prefer to call? 06 84 41 41 73